A new home construction schedule, phase by phase
This is the schedule HomeTakeOff starts a custom home from: 10 phases and about 36 weeks of workdays, from staking the lot to the final inspection. Use it as a starting point. Your plans, your trades, your inspector and the weather set the real dates.
- 10 phases, from site prep to final inspection
- About 36 weeks of workdays, a little over eight months
- Which phases overlap and which have to wait
- Free to use as a template in HomeTakeOff
Free during the beta. No credit card.
The phases and the week each one starts
Weeks count workdays, Monday to Friday, from the day you break ground.
Site preparation
- Starts:
- Week 1
- Main tasks:
- Survey and staking, clear and grade the lot, erosion control
Foundation
- Starts:
- Week 2
- Main tasks:
- Excavation, footings, foundation walls, waterproofing and backfill
Framing
- Starts:
- Week 7
- Main tasks:
- Floor, wall and roof framing, sheathing and housewrap
Roofing
- Starts:
- Week 13
- Main tasks:
- Shingles, flashing and gutters
Plumbing and electrical rough-in
- Starts:
- Week 15
- Main tasks:
- Rough plumbing and rough electrical, side by side
HVAC rough-in
- Starts:
- Week 16
- Main tasks:
- Ducts and equipment
Insulation and drywall
- Starts:
- Week 19
- Main tasks:
- Insulation, then drywall hang and finish
Interior finishing
- Starts:
- Week 23
- Main tasks:
- Paint, cabinets and countertops, flooring, trim and doors
Fixtures and trim-out
- Starts:
- Week 33
- Main tasks:
- Plumbing fixtures, light fixtures and devices, HVAC finish
Landscaping and closeout
- Starts:
- Week 33
- Main tasks:
- Grading and sod, driveway and walkways, final cleanup
Final inspection
- Starts:
- Week 36
- Main tasks:
- The last milestone before move-in
What overlaps and what waits
Some trades can share the house. Plumbing and electrical rough-in usually start together, with HVAC a few days behind. Other work has to wait: insulation waits for the rough-ins to pass inspection, drywall waits for insulation, and the plumber and electrician come back for fixtures once paint and cabinets are in.
Those waits are where a schedule slips. Link each task to the one it waits on, and when one runs late, the rest move with it instead of landing on top of each other.
What moves the dates
Plan for these before they happen, not after.
- Rain and cold on the foundation pour and the roof
- Inspections that don't come the day you call
- Lead times on windows, doors and cabinets
- A trade that's still on another job
- Selections and change orders that come in late
Use this schedule as a template
In HomeTakeOff this schedule is the Custom Home Build starter template, with a budget for each phase. Start a project from it, change the phases to fit how you build, and the dates count workdays from your start date. Save your version, and the next house starts from it.

Questions builders ask
How long does it take to build a new home?
It depends on the house, the market and the weather. Many custom homes take seven months to a year from breaking ground. The sample here is about 36 weeks of workdays, a little over eight months, before rain days and waits for inspections.
What is the order of construction for a new house?
Site preparation, foundation, framing, roofing, plumbing, electrical and HVAC rough-in, insulation and drywall, interior finishing, fixtures and trim-out, landscaping and closeout, then the final inspection.
Can I change the template?
Yes. Add, remove or reorder phases and tasks, change how long each one takes, and save it as your own template for the next house.